The big reason for why they need to go to the aircraft boneyards…
From the link:
Across the global electric power industry, gas turbine lead times have stretched to levels not seen in decades — and the implications are becoming impossible to ignore. If an energy company ordered a gas turbine today, the unit would, on average, not begin operating until 2031. These delays are no longer a temporary market disruption. They are becoming a structural constraint on how quickly utilities and developers can respond to rising electricity demand, extreme weather, and the retirement of aging generation assets.
Large natural gas turbines now require more than five years from order to delivery. Smaller turbines — historically the most flexible and responsive part of the fleet — now take 18 to 36 months. At the same time, costs have risen sharply. In just the past six months, EPRI research shows average gas turbine prices increased from roughly $2,000/kW to $3,000/kW, a nearly 50% increase. While inflation contributes to this rise, the larger driver is sustained stress across the global manufacturing supply chain.
~ ~ ~ ~ ~ ~ ~ ~
_ Pete
They could have clean solar + battery or clean wind + battery for power with no noise, easy to build and cheap.
Do you really think they didn’t consider the alternatives?
DB2
Many leaders in the AI rush for energy are not reliable or good at considering energy alternatives. Just look at the idiotic proposals that have been floated and approved.
Timing is critical. When the data center equipment is fully installed but waiting for grid connection, means to generate power at that moment can be the driver. Running backup diesel generators might be attractive. Used jet engines may be much faster to install. And might be temporary while they wait for cleaner or more reliable power.
Project planning usually includes time lines for every aspect. Looking for the soonest start date at acceptable cost.
Without regard to air pollution or noise pollution or diminution of surrounding inhabitants’ access to water, etc.
And now you understand how “regulation” comes to be.
Below is an analysis from the Royal Bank of Canada (RBC) on why natural gas is the energy source of choice for data center operators.
A few excerpts…
In our latest analysis, we forecast natural gas consumption from data centers reaching approximately 6.1 billion cubic feet per day by 2030 (versus 2024 levels), substantially higher than our previous expectations. This is due to a maturing development pipeline with a growing number of projects advancing toward completion and a notable geographic overlap between planned data center locations and the nation’s gassiest energy grids and most prolific natural gas basins.
And…
The appeal of natural gas for data center operators extends beyond simple economics. U.S. natural gas markets offer structural advantages that enhance predictability and reduce geopolitical risk, a critical consideration in today’s volatile energy environment.
While global natural gas prices have spiked dramatically in response to regional supply disruptions, U.S. Henry Hub prices have remained remarkably resilient and contained. European benchmark prices (TTF) have risen over 40% in response to Middle Eastern supply disruptions, and Asian liquefied natural gas prices have surged as geopolitical tensions threaten critical maritime chokepoints. By contrast, U.S. natural gas markets are largely insulated from international geopolitical shocks due to domestic supply abundance, significant storage capacity, and fully utilized (and thus naturally capped) LNG export capacity aside from planned additions through the end of the decade.
Finally, and to the point…
At the regional level, FERC issued a landmark order directing PJM to overhaul its transmission tariff framework. Under the new service options, data centers must now explicitly purchase generation firmness either through self-supply or formal transmission contracts with defined curtailment rights. Critically, this regulatory shift creates a structural bias toward firm generation sources like natural gas, which can reliably meet baseload capacity requirements, over intermittent renewables, which would require massive battery overbuilding to achieve equivalent firm capacity. For infrastructure investors, this regulatory framework effectively locks in long-duration natural gas contracting opportunities.
~ ~ ~ ~ ~ ~ ~
If solar + batteries or wind + batteries were truly better choices, then data center developers would be going with those renewable sources. Since they usually choose to go with natural gas, even with the long lead times for purchasing new combustion turbines, that tells me natural gas is currently the best way to quickly provide the 24/7 power that data centers require.
_ Pete
Can the used jet engines be adapted to burn natural gas? Or do they need jet fuel (ie kerosene)? Pipeline connection might take a year to construct, but turbine delay is major concern.
Easiest way to add pipeline capacity is add additional pipeline on existing right of way. New right of way might take longer but may not be big delay if distance is short. But all probably requires permits and that could take a while.
Yes, the article says they are converted. Have to be, actually. Jet fuel delivery is fraught, natural gas has substantial infrastructure already in place all over the country.
The problem is intermittency. Even with solar and batteries you’re going to need a tertiary backup, so it becomes a redundant cost. This is an issue for “small scale” operations (even as huge as they are) but less so for large scale utility systems, which already have multiple and sometimes redundant systems in place.
Yes natural gas is cleaner that coal, oil, and jet fuel. However, how many people want to live within a 5 to 10 mile distance from 10 Boeing 747 jet engines going full blast 24/7. That noise is horrible. I grew up (11-25) in Burbank, CA, where Lockheed had its main manufacturing, testing and airfield about two miles from my home. It frequently tested jet engines durinfg day and at night which would waken people. The those were the days of smaller jets. When Lockheed relocated out to the desert in Palmdale, the testing noise went away. But the Burbank airport grew into a major comercial airport. So the jet noise continued and is still going on in the beautiful downtown Burbank which is flush with movie and TV studios.
I do not think Governments, Bankers, Utilities and Big Tech companies have not been paying attention to the real environment problems with noise, air pollution, electrical power supplies and water usage requirements in locating and designing data centers. They want data centers to be near users, but that rquires power generation, air pollution and water useage near the data centers.
As we saw in the midterm elections, people do not want the noise, air pollution and water useage near them. The Governments, Bankers, Utilities and Big Tech need to alliviate these public concerns.
The data centers will be connected to the grid. There is no intermittancy problem with frid backup. Engineers can design the optimal use of renewables, batteries and the grid.
Jet engine turbine generators are not the answer. Combined cycle gas turbines are a much better solution with more efficiency, cheaper operation and less of the problems that stand alone jet engines and peakers bring to the power generation requirements.
Well, there’s the rub. The grid operators are taking reservations, and some of them are 8 to 10 years out. The average time for a grid connection on this scale is 5 years, and you can put a converted jet engine/generator in service in as little as 18 months - it can even be just a month if you already have the necessary hardware to do it.
That’s why they’re doing it. It’s not cheaper. It’s not more environmentally friendly. It’s not easier. It requires more maintenance. It’s louder. But you can get going a lot faster, which is important if you’re dancing with hot money.
Nothing about an old airliner jet engine prohibits it from being mounted to a skid, supplied with NG from a local market pipeline, routed to a high torque reduction gearbox to a generator, throttled by PLC to 60 Hz and placed with a HRSG downstream. Finally, if you want to reduce pollution, you could put a scrubber on it, too.
Nothing.
It’s only money.
Sloppy analysis on your part.
One jet engine is not enough for a data center. They need 10 or more for data center. The local natural gas lines cannot handle this amount ofnatural gas demand 24/7 for 10 engines.
While scrubbers are effective in reducing emissions, they can be expensive to install and maintain. They require a constant supply of water and may produce wastewater or sludge that needs proper treatment and disposal. Scrubbers can also consume energy, which will reduce the overall efficiency of a power plant.
Will the people allow these to be licensed in their local areas? I do not think they will. After they do this at one data center, the people will cry bloody murder. The data center will be required to shut them off and only use them for backup.
It has already been going on for a while. From the WSJ back in February…
How Jet Engines Are Powering Data Centers
https://www.wsj.com/business/energy-oil/how-jet-engines-are-powering-data-centers-b1c587a9
Jet engine leasing and repair company FTAI Aviation plans to start selling a modified version of the engine used in the Boeing 737 to power data centers this year…Jefferies estimates could add $750 million of earnings before interest, taxes, depreciation and amortization a year…Others pursuing this conversion include private equity-backed ProEnergy, which sells natural gas turbines that are adapted from the same engine that powers the Boeing 747…
Jet engines are a natural fit. Power equipment giants GE Vernova, Siemens Energy and Mitsubishi Heavy Industries already sell power turbines—known as aeroderivatives—that are modeled after these very jet engines…
FTAI Aviation’s President David Moreno said it takes the company 30 to 45 days to convert a jet engine to a power-generating turbine…They [FTAI and Boom Supersonic] said their turbines can be configured as combined cycle, which means a steam turbine is added to capture waste heat…So far, FTAI has said it expects to be able to deliver about 100 turbines, or 2.5 gigawatts, a year.
DB2
You wonder if the generator component is readily available or is it back ordered like other data center components.
If available, permitting might be biggest delay. Noise seems to be the greatest concern. Is noise cancellation possible?
Carbon dioxide could be scrubbed from the gas stream. Usually high boiling amines like propanolamine are used, not water. The CO2 can be recovered by heating for collection and sequestration. This is common in ammonia plants where CO2 from synthesis gas is removed to produce hydrogen. The captured CO2 is often sold for uses like carbonated beverages.
Lime slurries can be used to scrub carbon dioxide but that makes no sense because lime is made by calcining limestone to release carbon dioxide. (Detail: limestone is calcined to quicklime CaO which is slaked in water to make lime Ca(OH)2.)