Here’s an issue I had not heard about before: Phantom data centers.
In short, when a data center is planned, they look for power. A because different providers have different timelines and capabilities, the prospective owners may solicit from multiple power companies, as many as 3 or 4.
So those power companies have to factor into their building that power request, except oops, it may not materialize at all - for any of them as some data centers choose to build their own power stations.
Meanwhile the utilities have put inflated and possibly bogus capital requests on their books, taken it to regulators, and solicited capital in the bond markets.
More detail, likely better too, in today’s WSJ article:
Phantom’ Data Centers Are Demanding More From the Power Grid Than They Need
Utilities are imposing higher electricity rates and collateral requirements to identify legitimate data-center projects
Data-center developers are turning to utilities and grid operators for unprecedented [amounts of electricity].The power industry is countering with a perhaps surprising question of its own: Are you for real?
The [artificial-intelligence boom] is driving a once-in-a-generation surge in electricity demand that should translate to a heyday for utilities. Yet the race has accelerated so quickly that it has become challenging to distinguish projects that are ready to build from those that might never materialize.
To plan their own investments and shield other customers, utilities are trying to filter out legitimate projects from wannabes by imposing higher electricity rates, longer-term contracts, collateral requirements and steep fees for engineering studies.
Utilities face a predicament: Underbuilding grid infrastructure risks missing a huge opportunity, but overbuilding could also be problematic. Because grid costs are shared, other electricity customers would be left to pick up the tab—and help a utility recoup its investment—if a data-center project falls through.
Under normal circumstances this might be a slight economic “oops”, but with the scale of these things driving the entire economy it could be a massive imbalance of capital allocation, industry costs, and ultimately consumer power bills. One source in the article notes that just 23% of such requests are considered “high confidence”, but they must plan for all of them anyway.