Good news, for Ontario Power that owns Darlington. Meanwhile Bruce Power is in the process of refurbing their eight reactors over a long timeline.

https://www.world-nuclear-news.org/Articles/Milestone-as-rea…

Milestone reached as Darlington refurbishment is ahead of schedule

16 August 2022

Fuel channel installation has been completed at Darlington unit 3, and the unit is now expected to return to service by late 2023 - several months earlier than planned - Ontario Power Generation (OPG) has announced. The unit is the second of four Darlington units to undergo a mid-life overhaul.

https://www.opg.com/powering-ontario/our-generation/nuclear/…

https://www.brucepower.com/life-extension-program-mcr-projec…

Bruce is privately owned partly by TC Energy a very large pipeline company. I suppose that makes me part owner in an eight reactor Nuclear power plant as well as a lot of big pipelines and a very nice 5.53% dividend? }};-D

Tim

3 Likes

I suppose that makes me part owner in an eight reactor Nuclear power plant as well as a lot of big pipelines and a very nice 5.53% dividend? }};-D

Tim

You appear to be glowing :wink:

Restarted my Canadian Amazon wannabe, aka, Shopify (SHOP) today

Restarted my Canadian Amazon wannabe, aka, Shopify (SHOP) today

Looks like an interesting candidate for selling covered calls…

https://bigcharts.marketwatch.com/advchart/frames/frames.asp…

The Captain